DC2_CV24b

Results File
Dataset
File Header

Author(s):Vanhoucke, M. and Coelho, J.
Reference:Vanhoucke, M., & Coelho, J. (2024). A matheuristic for the resource-constrained project scheduling problem. European Journal of Operational Research, 319(3), 711725. https://doi.org/10.1016/j.ejor.2024.07.016
Date:01/12/2024
Hardware / software: STEVIN HPC-UGent infrastructure, C++, compiler intel/2017.02, Linux
Stop criteria(s):Best results from all runs
Submission date: 2024/04/08

Statistics
Nothing changed since there are no new lower bounds, upper bounds nor optimal solutions.
Instances: 11
Upper Bounds: 11
- Average deviations:
- over CPM: 308.67%
- over best LB: 3.09%
- over best UB: 0.10%
- Best Known: 10 (90.91%)
- Closed (using best LBs): 1 (9.09%)
- Sum of time units: 2019
- Open time units:
- to LBs: 60 (3.06%)
- to UBs: 2 (0.10%)
Date