J90_CV24b

Results File
Dataset
File Header

Author(s):Vanhoucke, M. and Coelho, J.
Reference:"working paper ""A matheuristic for the resource-constrained project scheduling problem"""
Date:2024
Hardware / software: STEVIN HPC-UGent infrastructure, C++, compiler intel/2017.02, Linux
Stop criteria(s):Best results from all runs
Submission date: 2024/04/08

Statistics
New results:
3 new upper bounds
3 open instances updates (upper and lower bounds)
Results saved in sites/default/files/datasets/J90.csv
BKS saved in sites/default/files/datasets/J90_BKS.csv
Instances: 3
Upper Bounds: 3
- Average deviations:
- over CPM: 65.79%
- over best LB: 5.88%
- over best UB: 0.00%
- Best Known: 3 (100.00%)
- Closed (using best LBs): 0 (0.00%)
- Sum of time units: 398
- Open time units:
- to LBs: 22 (5.85%)
- to UBs: 0 (0.00%)