J120_DV

Results File
Dataset
File Header

Author(s): Debels, D. and Vanhoucke, M.
Reference:Debels, D., & Vanhoucke, M. (2007). A Decomposition-Based Genetic Algorithm for the Resource-Constrained Project-Scheduling Problem. Operations Research, 55(3), 457-469. https://doi.org/10.1287/opre.1060.0358
Date: 2007/01/01
Hardware / software: Stevin Supercomputer Infrastructure, C++, compiler intel/2017.02, Linux
Stop criteria:cumulated results from several runs, on open instances only. Maximal run: 1000 runs x 500k schedules
Submission date: 2017/5/21

Statistics
Nothing changed since there are no new lower bounds, upper bounds nor optimal solutions.
Instances: 409
Upper Bounds: 409
- Average deviations:
- over CPM: 42.57%
- over best LB: 2.97%
- over best UB: 0.31%
- Best Known: 252 (61.61%)
- Closed (using best LBs): 108 (26.41%)
- Sum of time units: 54687
- Open time units:
- to LBs: 1888 (3.58%)
- to UBs: 184 (0.34%)