J120_CV24c

Results File
Dataset
File Header

Author(s): Coelho, Jose and Vanhoucke, Mario
Reference: Coelho, Jose and Vanhoucke, Mario. 2024. Working paper 'Comparing and extending satisfiability solution methods for the resource-constrained project scheduling problem'
Date: 2024/10/20
Hardware / software: STEVIN HPC-UGent infrastructure, C++, compiler intel/2017.02, Linux
Stop criteria(s):Several procedures and stop criteria, the last one with 20 hours.
Submission date: 2024/10/20

Statistics
Nothing changed since there are no new lower bounds, upper bounds nor optimal solutions.
Instances: 600
Optimal results: 299 (49.83%)
Upper Bounds: 600
- Average deviations:
- over CPM: 31.94%
- over best LB: 3.54%
- over best UB: 1.65%
- Best Known: 365 (60.83%)
- Closed (using best LBs): 305 (50.83%)
- Sum of time units: 74874
- Open time units:
- to LBs: 3403 (4.76%)
- to UBs: 1699 (2.32%)
Lower Bounds: 599
- Average deviations:
- over CPM: 24.59%
- below best LB: 0.83%
- below best UB: 2.51%
- Best Known: 372 (62.00%)
- Closed (using best UBs): 313 (52.17%)
- Sum of time units: 70561